Selected delay and programme appointments.

Construction claims and disputes are often confidential, so the appointments below are anonymised and the instructing parties are not identified. The relevant project context, the scope of each appointment and verified outcomes are described where appropriate: together they span adjudication expert evidence, a major international LNG development, long-distance linear infrastructure and offshore renewables.

Case file / 01 · UK adjudication · Independent delay expert instructed through the referring party's solicitors

Extension of Time awarded in full following independent retrospective delay analysis

Sector
Civils & remediation
Region
United Kingdom
Forum
Adjudication

The situation. A dispute arose from remediation and infrastructure works on a substantial development project. The parties disagreed about actual progress, the nature and timing of the events affecting delivery, the extent of the resulting delay and the causes properly responsible for it. An independent analysis was required within the compressed timetable of adjudication.

The appointment. Instructed through the referring party's solicitors, Ionut Voinea undertook an independent retrospective delay analysis: reviewing the available project and programme information, reconstructing actual progress, investigating the nature and extent of delay, identifying its material causes, assessing the effect on completion and preparing an independent expert delay report for the proceedings.

Outcome

The adjudicator preferred the expert analysis and awarded the full Extension of Time period assessed in the report.

Relevant services: Expert Witness Services · Forensic Delay Analysis

Case file / 02 · Major claims support · Acting for the contractor

Delay analysis on a US$500m+ claims portfolio for a major LNG development

Sector
Offshore energy & LNG
Region
Middle East
Claims
US$500m+

The situation. The contractor was delivering works within a major natural gas expansion programme intended to increase LNG production for export: wellhead topsides, offshore pipelines, subsea cables and associated onshore pipeline works. Delay and interface issues arose across technically complex packages, producing a portfolio of substantial contractual claims.

The appointment. Delay analysis and forensic planning support on several of the contractor's principal claims: examining programmes and project records, assessing the causes and consequences of delay, reviewing the developing critical path and providing a clear and structured technical presentation of the time-related position, within the wider context of package interfaces and outstanding deliverables.

Outcome

The delay support contributed to significant Extension of Time relief and a favourable commercial settlement.

Relevant services: Extension of Time Claims and Delay Support · Forensic Delay Analysis

Case file / 03 · Retrospective delay analysis · Acting for the main contractor

Retrospective delay analysis on a 580-kilometre gas pipeline

Sector
Gas transmission
Region
Western Australia
Project
DN300 · ~580 km

The situation. The main contractor was advancing a delay and disruption claim from the construction of a major long-distance gas pipeline. The linear nature of the works created a complex programme environment: extensive geographical sections, moving work fronts and many concurrent construction activities.

The appointment. An independent retrospective delay analysis addressing the causes and effects of delay, reviewing the programme and project records against the actual sequence of construction and drawing on time-distance techniques suited to linear works. Relevant events were investigated to establish their relationship with progress and their effect on the time required to complete.

Outcome

The analysis supported the contractor's wider claim, which resulted in significant Extension of Time relief and a favourable commercial settlement.

Relevant services: Forensic Delay Analysis · Extension of Time Claims and Delay Support

Case file / 04 · Live & retrospective support · Acting for the contractor

Delay assessment and claims support on a major offshore wind farm

Sector
Offshore renewables
Region
Western Europe
Role
Contractor appointment

The situation. A specialist contractor required continuing support in assessing the programme consequences of delay events on a major offshore wind farm: a multi-turbine installation of several hundred megawatts, located some distance offshore and still under construction. With the project still active, the need was twofold: a contemporaneous understanding of emerging delay exposure, and retrospective analysis of events that had already affected progress.

The appointment. Ongoing delay and planning support: reviewing developing programme information and actual progress, assessing whether identified events affected critical or near-critical activities, carrying out retrospective analysis where sufficient project history existed and supporting contractual positions where the records allowed, helping the project team distinguish emerging programme risk from positions supported by the available records.

Value delivered

A structured, evidence-based foundation for assessing and advancing multiple delay-related contractual positions on a live project.

Relevant services: Programme Advisory and Assurance · Extension of Time Claims and Delay Support

Representative appointments · instructing parties not identified · cases anonymised · project characteristics and verified results stated where appropriate

“Different projects, different forums and different contractual questions. The consistent requirement is analysis that connects the event, the programme, actual progress, the supporting records and the conclusion.
The common thread

Casework spans live project support, claim preparation, retrospective delay analysis, expert evidence, rebuttal and support through formal proceedings. Each appointment begins by establishing what the available records can support.