The method follows the question, the records and the project history.

No single delay analysis method is appropriate for every matter. The analytical approach depends on the question to be answered, the contractual context, whether the assessment is contemporaneous or retrospective, the quality of the programmes and records, the actual progress information and the intended use of the findings.

First principles

Three working principles.

C/01

The records come first

The analysis starts with the available programmes, project records and actual progress, and follows them to a conclusion. Conclusions follow the information rather than a preferred position; where the information does not support the position hoped for, we say so early.

C/02

The approach fits the question

Contemporaneous or retrospective, prospective or as-built based, each analytical approach answers a different question and needs different records. The approach is selected to suit the question, the timing, the contractual context and the available information, and the selection is explained.

C/03

Assumptions and limitations are visible

Material findings are connected to the relevant source information. Assumptions, reconstructed information, gaps and areas of uncertainty are identified expressly, so the reader can see what each conclusion rests on.

Methods and reference frameworks

Recognised methods, used as a guide.

The SCL Delay and Disruption Protocol (2nd Edition) and AACE International RP 29R-03 are recognised reference materials for delay analysis: guidance rather than mandatory rules. The overview below is a guide, not a rigid decision table.

MethodWhat it establishesBest suited when
Time Impact Analysis The forecast effect of a delay event, modelled into the programme current at the time it arose. Prospective EoT · Good updates exist
Windows / Time Slice How the critical path actually moved through successive periods, with causes attributed window by window. Retrospective · Regular progress data
As-Planned vs As-Built Where and by how much actual progress departed from the planned intent, tied to the events responsible. Records limited · Clarity paramount
Collapsed As-Built What completion would have been achieved but for specified events, extracted from the as-built record. Strong as-built data · But-for questions
Impacted As-Planned The theoretical effect of events on the baseline programme; used with care and stated as such, given its known limitations. Early-stage · Limited progress records
Time-Distance Analysis Progress and delay along the alignment of linear works, plotted against location and time. Linear projects · Pipelines, rail, roads

Method selection is not determined by labels alone. Methods may need adaptation, combination or supporting analysis depending on the available records, and critical and longest-path assessment, float and concurrency analysis and programme-version comparison support whichever method is applied. See TIA vs Windows Analysis and Forensic Delay Analysis.

SoftwarePrimavera P6 · Asta Powerproject · Microsoft Project
ReferenceSCL Protocol 2nd Ed. · AACE RP 29R-03
ContractsNEC · JCT · FIDIC

Evidence assessment

How the programme evidence is assessed.

The relevance and weight of each item depend on its timing, reliability, consistency, provenance and its connection to the issue being analysed, rather than on a fixed hierarchy.

E/01

Native programme data

Baseline and update programmes with their history, logic and float, read in their native form wherever possible.

Programme record
E/02

Progress and site records

Progress records and contemporaneous reports, site diaries, photographs, production information and as-built data.

Site record
E/03

Correspondence and contract records

Correspondence, notices, instructions, RFIs and meeting records: the contractual and factual context the events sit in.

Contract record
E/04

Witness and reconstructed information

Used where contemporaneous records are incomplete, identified as such, tested for consistency and never silently blended with the record.

Identified expressly

Unsupported assertions are not treated as established facts: statements about delay are tested against the available records before they are relied on.

Consultancy and expert roles

Two roles, kept clearly distinct.

When appointed as an independent expert witness, the overriding duty is owed to the relevant court, tribunal or decision-making forum. Opinions remain independent of the appointing party, applicable procedural requirements, including CPR Part 35 where relevant, are followed, and expert work is kept separate from consultancy support on the same matter where independence may be affected. See Expert Witness Services.

Independent expert appointments - ProTech Planning
D/01

Consultancy and advisory work

Objective specialist analysis within the agreed scope: strengths, weaknesses, gaps and limitations identified candidly, so decisions are made on an accurate technical picture. This role carries no overriding duty to a tribunal and is distinct from expert evidence.

D/02

Conflicts checked, always

Every appointment begins with a conflict check across parties, projects and prior instructions, so the applicable role and any independence constraints are established before the engagement.

Technology & controls

Technology improves the process. Expertise determines the conclusion.

Controlled technology and AI-assisted workflows help the practice work efficiently across large programmes and record sets. They inform the analysis; they do not replace the judgement that reaches the conclusion.

Assisted workflows may help with programme comparison, detection of activity, date and logic changes between revisions, document organisation, chronology preparation, evidence referencing, data validation and quality checks. Every step sits inside a controlled process:

  1. 01

    Project records

    The source records: native programmes, updates, correspondence and site information. These remain authoritative throughout.

  2. 02

    Structured processing

    Records and data are organised and prepared, using technology to handle volume reliably.

  3. 03

    Programme & data analysis

    Programme comparison and change detection surface what moved, when and where.

  4. 04

    Professional verification

    Automated findings are checked back against the source records before they are relied on.

  5. 05

    Expert judgement

    Causation, criticality, concurrency and conclusions are determined by the responsible specialist.

  6. 06

    Client deliverable

    Findings prepared for their purpose, every material conclusion reviewed before release.

In short: technology supports the process; the source records and the responsible specialist control the conclusion.

“Complex analysis, clearly explained. Reports distinguish facts, assumptions, analytical steps, limitations and conclusions, and use timelines and programme illustrations where they improve understanding, so commercial teams, lawyers and decision-makers can follow the analysis as readily as planners.”
On clarity - ProTech Planning

Put the approach to work

Tell us the question, and what records are available.

An initial discussion can identify the appropriate scope, the information that will be needed and the analytical route. Initial discussions are confidential, and enquiries are acknowledged within one business day.